Element 25 Advances Butcherbird Manganese Project Expansion

Element 25 Butcherbird manganese project


Butcherbird Mine Expansion Targets 1.1Mtpa Production

Element 25 has accelerated the Butcherbird manganese project expansion in Western Australia. The project aims to increase manganese concentrate output to 1.1 million tonnes per annum (mtpa). As a result, updated feasibility studies confirm enhanced operational efficiency and long-term profitability.

Altris Engineering leads the engineering work alongside Element 25. Meanwhile, process improvement studies continue to optimize cost savings and execution flexibility. In addition, critical mining equipment, including mineral sizers and a log washer, has been secured.


Financing, Ore Reserves, and Strategic Objectives

Element 25 raised A$10 million through placement and secured a A$50 million senior debt facility. Furthermore, ongoing offtake negotiations target both steel market supply and future battery-grade manganese sulphate monohydrate production.

The updated ore reserve at Butcherbird increased by 107% to 101.4mt at 10.4% manganese. Consequently, the life-of-mine extends beyond 18 years at 1.1mtpa. Measured and indicated resources surged 142%, reaching 130mt at 10.23% manganese. These developments strengthen Element 25’s supply strategy for traditional steel markets and emerging battery applications.

The Butcherbird expansion complies fully with the Western Australia regulatory framework. Approvals include the WA Department of Water and Environmental Regulation and the WA Department of Energy, Mines, Industry Regulation and Safety.


ScrapInsight Commentary

Element 25’s Butcherbird expansion significantly increases manganese supply security for steel and battery markets. The 18-year mine life and improved ore reserves suggest stable pricing potential. Regulatory compliance ensures project continuity while supporting Australia’s strategic resource position.